The doors to our Whitianga and Paeroa offices will be closed for the summer break from 4pm on Friday, 20 December, while our Taupō and Hamilton offices will close for the summer break at 1pm on Tuesday, 24 December. All offices will reopen on Monday, 6 January 2025. To report air or water pollution, unsafe water activities in or on a river, lake or harbour, or make a general enquiry or information request during this time, call us 24/7 on 0800 800 401.

Close alert

Lower Waikato stopbank upgrades

Funded: $5.22m
Total cost: $10m
Project starts: 2024/25
Project ends: 2026/27

This project involves raising the levels of up to 13.8 kilometres of stopbanks in the Tūakau area in the lower Waikato River catchment to allow for protection against a one in 100-year flood event. The upgrade is the result of a scheme review that included modelling to determine future climate change requirements.

Status update:

  • Design completed and approved in November 2023.
  • Procurement of construction services ready for tender, with construction to begin in the 2024/25 construction season.